Installer walks from the gate to the mounted mast on the wall
Installer climbs ladder and places the dish on the mast
Check elevation against work order
[Post-production: Create photograph of work order; use call out to show elevation listed on the order]
Show elevation scale with pointer at the elevation
Show Skew at 90 degrees.
Check Cam set to zero
Show the Cam from below with notch and hash mark aligned
Check mast flange nuts allow the install to gently swing dish
Show the dish swing gently from side to side
Show that test cables are unmarked, and used with tools
[Post-production: Create a photo showing two coiled test cables, the APA, and the SSLM in a group on a plain background.]
Attach test cables to tools and set aside
Installer takes one coiled test cable and attaches to the "From TRIA" port on the APA
Installer takes one coiled test cable and attaches to the "To Modem" port on the APA, and then to the LNB port on the SSLM
Show how the installer sets this to the side
Attach TX to TRIA, then ground block, then TX on modem
Installer takes one green cable and attaches to the TX on the TRIA
Installer attaches this green cable to ground block
Installer attaches the second green cable, and attaches to the ground block
Attach RX to TRIA, then ground block, then modem
Installer takes one red cable and attaches to the RX on the TRIA
Installer attaches this red cable to the ground block
Installer attaches the second red cable to ground block
[During post-production, add in Interior shots of attenuators and modem power up, listed below]
Add tools to TRIA
Remove RX cable from TRIA and attach test cable from APA
Installer removes the red-labeled RX cable from TRIA
Installer picks up the tool set
Installer connect the "From TRIA" test cable (which is also connected to the APA) to the RX port on the TRIA
Installer connects the red-labeled RX cable to the Sat RX port on the SSLM
Add tools to modem
Attenuators
Show the 20 dB attenuator
Show the 10 dB attenuator, then the Installer attaches the 10 dB to the 20 dB
Installer attaches to Modem - Need this shot
Installer connects 20dB to the RX port on the modem
Attach a red-labeled cable to the attenuators
Attach a green-labeled cable to TX port on the back of the modem
Installer plugs in modem
Set Inclinometer and lay on Boom Arm (Point Elevation)
[Post-production: Create photograph to show AA from the work order]
Show setting the Inclinometer to the AA
Show putting the Inclinometer on the Boom arm
Loosen Elevator bolts & nuts
Show the 1/2" open wrench and the 1/2" ratchet
Installer loosens the elevator bolts and nuts with the tool of his choice
Move lower Elev. nut until Inclinometer aligns correctly
Show the 1/2" open wrench sweeping on the lower elev. nut
Show the Inclinometer moving to the setting
Tighten Elev. nuts & bolts
Installer hand-tightens the upper elev. nut
Installer uses the 1/2" tool of his choice to tighten bolts on the elevation slots
Find the satellite in the sky (Point Azimuth)
Installer sets the SSLM gain to 60
[Post-production: Create photograph showing the satellite designation from the work order]
[During post-production, insert slide that shows the relative position of the 3 sats in the sky]
From front, show Installer swinging dish 10 degrees away from Sat, then brining it back
Show SSLM during that action (SSLM rises, then drops, then comes back to top. Stop at top.)
Tighten mast bolts
Installer uses the 1/2" tool of his choice to tighten bolts on the mast from the top to bottom.
Set the Cam (Peak Azimuth)
Installer sets the SSLM gain to 60
Show from below, Installer uses the 1/2" ratchet to loosen the AZ base
[During post-production, insert slide that warns about turning the Cam correctly]
Show from below, turn the Cam in a clockwise manner at least two full rotations
Show the SSLM during that action (SSLM rises, then drops, then comes back to top. Stop at top.)
Tighten the AZ base bolts
Show from below, Installer uses the 1/2" ratchet to tighten the AZ base bolts
Sweep and Count (Peak Elevation)
Installer sets the SSLM gain to 60
[Post-production: Duplicate file 12.2_19.2_LoosenElevPointElev.MTS, and edit to stop after loosening top nut on elevation rod]
Show the Installer using the 1/2" tool of his choice to loosen the elevation nuts on the arched slots
Show the Installer using the 1/2" tool of his choice to loosen the nuts on elevation rod
Show the SSLM dropping and leveling off
Show the 1/2" open wrench sweeping on the lower elev. nut in the direction that makes the SSLM drop completely (8 1/2-sweeps)
Show the 1/2" open wrench sweeping on the lower elev. nut in the opposite direction, counting each 1/2-sweep as the SSLM peaks and then drops to the reading in Step 6.
[During post-production, add in text overlay showing a count 1 ... 2 ... 3 ... etc with each 1/2-sweep ... 16 total]
[During post-production, add in a text overlay showing that the count is divided in half]
Show the 1/2" open wrench sweeping on the lower elev. nut in the first direction, 1/2 the 1/2-sweep count ... 8 1/2-sweeps)
Tighten Elev. nuts and bolts
Installer tightens the upper elev. nut with the 1/2" open wrench, adding an extra 1/4 turn to lock the nut
Installer uses the 1/2" tool of his choice to tighten bolts on the elevation slots
Push/Pull test
Shooting from the front, show Installer pushing the back of the dish from the top, and from each side.
Show the SSLM during that action (SSLM drops, then comes back.)
Dressing for Initial Modem Lock (Exterior)
Installer powers off the modem.
Installer removes test cable from RX port on the TRIA
Installer removes red-labeled cable from Sat RX on the SSLM
Installer connects the red-labeled cable to the RX port on the TRIA
Dress for Initial Modem Lock (Interior) - need this shot
Remove red-labeled cable from the Attenuators
Attach red-labled cable to the "From TRIA" port on the APA
Attach test cable on the "To Modem" port of the APA to the Attenuators
Green-labled cable remains attached to the TX port on the modem
Plug in modem
Initial Modem Lock
Off-camera: Modem is plugged in
Modem lock
[Post-production: Callout that no Ethernet is NOT connected]
Dressing for Final Modem Lock (Interior) - Need this shot
Installer unplugs modem
Installer removes APA and Attenuators from the RX port on the modem
Installer removes the red-labeled cable from the Attenuators
Installer connects the red-labeled cable to the RX port on the modem
Installer connects Ethernet cable
Installer plugs in the modem at the wall
Final Modem Lock
Off-camera: Modem is plugged in wall
Modem lock
[Post-production: Callout that Ethernet cable IS connected]
Interior Shots for Point & Peak
Attenuators
Show the 20 dB attenuator
Show the 10 dB attenuator, then the Installer attaches the 10 dB to the 20 dB
Installer attaches both attenuators to the RX port on the back of the modem
Attach a red-labeled cable to the attenuators
Powering the Modem
Installer plugs in modem
Installer unplugs the modem at the wall
Initial Modem Lock
APA and Attenuators
Show the modem powered down at the wall
Show the attenuators still attached to the RX port
[During post-production, add in a text overlay noting that the Installer has moved inside]
Show red-labeled cable coming from wall penetration to the "From TRIA" port on APA
Show test table connected from the "To Modem" port on the APA to the Attenuators on the modem
Modem Lock
Use unprovisioned modem
Installer powers up modem at the wall
Show LEDs as it locks.
Normal Modem Lock
Swap to a provisioned modem, add attenuators, power it, and allow it to lock
Dressing for Normal Modem Lock
Installer powers off the modem at the wall.
Installer removes the APA and the attenuators from the modem
Installer attaches red-labeled cable to the RX port on the modem
Exterior Shots for Point & Peak
Interior Shots for Point & Peak
Initial Modem Lock
Normal Modem Lock